← Technical resourcesEngineering Guide 02

How to select the right
MCC panel.

Coordinate motor ratings, starter types, protection, control philosophy, fault level, construction and communication before issuing the MCC enquiry.

Nextgen MCC panel lineup ready for project dispatch
Original Nextgen assemblyManufactured, inspected and prepared for dispatch.

Start with the motor schedule,
not the enclosure size.

An MCC is selected from the connected motors and their operating philosophy. Confirm each motor's rating, duty and starting method; then coordinate protection, control, busbars, fault withstand, feeder construction, cable entry, communication and maintenance access against the approved SLD and project specification.

Illustrative DOL motor starter assembly with protection, contactor and overload relay

DOL

Direct full-voltage starting for suitable smaller motors.

Illustrative star-delta motor starter assembly with three contactors

Star-Delta

Three-contactor arrangement used to reduce starting current.

Illustrative three-phase soft starter assembly

Soft Starter

Controlled voltage ramp for smoother motor acceleration.

Illustrative variable frequency drive assembly

VFD

Variable frequency and speed for process control.

Illustrative equipment arrangements. Final component selection and wiring must follow the approved SLD, motor schedule and project specification.

Selection pointDOLStar-DeltaSoft StarterVFD
Starting methodFull-voltage direct startReduced-voltage transitionControlled voltage rampVariable frequency and speed
Typical useSmaller motors where starting current is acceptableMotors requiring lower starting currentSmooth starting and reduced mechanical stressSpeed, process and energy control
Starting currentHighest of the four optionsLower than DOL during startElectronically limitedControlled through the drive
Speed controlNoNoNo continuous speed controlYes
Main considerationSupply capacity and voltage dipMotor terminals, transition and torqueBypass, cooling and application dutyHarmonics, cooling, cable length and process duty

Understand the panel
before selecting it.

The exact compartment layout changes with the approved SLD and feeder schedule, but these four areas help explain a typical MCC lineup.

Front view of an operational Nextgen MCC panel showing feeder compartments and controls
Representative Nextgen MCC front arrangement
01

Incoming and busbar section

Receives and distributes power. Rating is coordinated with design current, fault level, temperature rise and the approved SLD.

02

Motor feeder compartments

Each motor feeder is selected around the motor rating, starter method, protection and isolation philosophy.

03

Control and indication

Push buttons, selector switches, meters and status lamps support local operation and clear fault or running indication.

04

Cable and interface zone

Cable entry, terminal access and PLC, BMS or SCADA interfaces are planned for safe installation and maintenance.

Six checks before
you release the RFQ.

The correct MCC arrangement comes from coordinated electrical and process information. Final ratings and component selection must follow approved project documents.

01

Prepare the motor schedule

List motor rating, full-load current, duty, starting method, service factor, operating sequence and essential or non-essential classification.

02

Confirm the system data

Define system voltage, frequency, fault level, earthing arrangement, transformer or DG source and the applicable protection philosophy.

03

Select each feeder

Coordinate breaker or fuse, contactor, overload relay, control supply, indications and starter type with the motor and process requirement.

04

Define the control philosophy

Confirm local or remote operation, auto/manual modes, permissives, interlocks, emergency stops and interfaces with PLC, BMS or SCADA.

05

Choose construction

Review fixed or draw-out arrangement, segregation, cable entry, busbar rating, enclosure size, IP protection and maintenance access.

06

Plan testing and documents

Agree drawings, feeder schedule, component makes, routine checks, inspection points, communication map and handover documentation.

Design for operation
and maintenance.

Construction choices affect safety, footprint, maintainability, continuity of service and future expansion.

Clean front view of a completed Nextgen MCC panel
Completed Nextgen MCC front arrangement

Fixed feeders

A practical arrangement for many commercial and utility applications where compact construction and straightforward maintenance are suitable.

Draw-out feeders

Selected where rapid isolation, replacement and continuity of service justify withdrawable functional units and associated shutters or interlocks.

Form of separation

Chosen from the project specification and required separation between busbars, functional units and cable terminals.

Busbar system

Copper or aluminium busbars are rated from current, fault withstand, temperature rise, enclosure conditions and approved project data.

Enclosure and IP

Indoor or outdoor location, dust, moisture, ambient temperature, ventilation and cooling requirements determine enclosure protection.

Planning reference

Common questions
before engineering.

Use these answers for initial planning. Final MCC design must be reviewed against the approved SLD, motor schedule and operating philosophy.

01What information is needed to select an MCC panel?+

Provide the SLD, motor schedule, load list, system voltage, fault level, starter philosophy, control schematic, approved makes, communication requirement, construction type, project location and delivery programme.

02When should a VFD feeder be selected?+

A VFD is considered when variable speed, process control, soft acceleration or energy optimisation is required. Motor duty, harmonics, cooling, cable length, bypass philosophy and the operating environment must also be reviewed.

03What is the difference between fixed and draw-out MCC construction?+

Fixed feeders remain connected in their compartments and are isolated through the associated device. Draw-out units can be moved between connected, test and isolated positions where the approved design permits, supporting faster replacement and maintenance.

04Can an MCC communicate with PLC, BMS or SCADA?+

Yes. Feeder status, trip indication, metering and control can be coordinated through hardwired signals or approved communication protocols, depending on the component selection and project architecture.

05How is MCC busbar rating selected?+

Busbar rating is checked against design current, diversity, temperature-rise limits, short-circuit withstand, enclosure arrangement, ambient conditions and the applicable approved standard and project specification.

06Which tests are completed before dispatch?+

Checks typically cover construction, component ratings, wiring, identification, continuity, insulation, mechanical operation, interlocks, indications and applicable functional sequences. The agreed inspection plan governs final verification.

READY FOR TECHNICAL REVIEW?

Share the SLD, motor schedule and control philosophy.

Nextgen will review the available project information and coordinate the MCC feeder arrangement, starter types, protection, construction and interfaces.

Start MCC panel enquiry →

Start a conversation

Have a project in mind?
Let's engineer it right.

Share your SLD, BOQ or project requirement. Our team will respond with the right technical direction.